Back to listings

Thatcher

Reference: ST0821
Version: 1
View on Institute for Apprenticeships
Apprenticeship Standards available with Tresl

Interested in a simple Skills Scan and Learning Progress Tracker tool for the Thatcher standard?

Knowledge

  • K1: How materials are produced, grown, harvested, stored, prepared and transported inlcuding long straw, combed wheat reed (CWR) and water reed. Recognising the quality variance.
  • K2: What fixing method is appropriate including spars, screws and wires, crooks, pins, stitching. Understanding of spar production.
  • K3: The use, maintenance and correct storage of hand tools, associated tools and equipment including ladders.
  • K4: Health and safety: compliance with working at height regulations, outdoor working and suitability of weather conditions. Manual handling techniques. Why, when and how health and safety control equipment should be used when undertaking thatching work including personal protective equipment (PPE) and respiratory protective equipment (RPE).
  • K5: The relevant building, conservation and fire safety regulation affecting thatched buildings. Planning instructions, drawings, product information, specifications and how to interpret them.
  • K6: Understanding of the various building types including historic, new-build, commercial, residential. The sympathetic approach to historic and listed buildings; maintaining the local and vernacular character and techniques.
  • K7: How to safely load, transport, unload and store thatching materials. How to safely protect thatching materials from vermin and inclement weather.
  • K8: The selection of appropriate materials for particular thatching work.
  • K9: How to assess the condition of the roof and to prepare the roof for thatching.
  • K10: The selection and preparation of thatching materials for installation on the roof for particular thatching work including architectural details and features.
  • K11: The process of fixing appropriate thatching materials to various roof structures and features and to a competent standard.
  • K12: The importance of finishing works and projects to an acceptable standard including clearing site of tools, equipment and materials to customer satisfaction.
  • K13: The assessment of thatched roofs and how to quantify thatching and associated roof works and materials.
  • K14: Understanding the economics and responsbilities of running a thatching business.
  • K15: Understanding the methods of adjoining the other materials such as lead, slate, tiles, flat roof, fiberglass, corrugated roof, brickwork and stonework.

Skills

  • S1: Interpret instructions and information to plan, organise and carry out healthy, safe, productive and efficient working practices.
  • S2: Organise work, obtain and provide information. Ensure work is completed within the economic expectations of the organisation and that wastage of materials is minimised. Ensure that work methods optimise the use of time and that own work is coordinated with relevant others.
  • S3: Access, interpret and use drawings and specifications to carry out thatching work.
  • S4: Working safely and effectively with others. Develop and maintain productive working relationships with colleagues on a daily basis, communicate with customers/visitors/colleagues. Offer constructive views and ideas on developing and maintaining productive working relationships.
  • S5: Work safely, and be aware of key health, safety and welfare issues. Ensure that own work practices conform to organisational requirements, current legislation and official guidance, and minimise risk of injury and ill health to self and others.
  • S6: Work safely at height and use access equipment. Ensure that own work practices minimise the risk of damage to the surrounding environment, equipment, materials and components.
  • S7: Use, maintain and correctly store thatching tools and any associated equipment.
  • S8: Quantify thatching work and materials, and select the appropriate materials for particular thatching work, ensuring that the materials are suitable for intended purpose.
  • S9: Safely load, transport, unload and store thatching materials. Store materials correctly and give adequate and effective protection against vermin and weather conditions. Ensure materials are accesible when required for use.
  • S10: Prepare appropriate thatching and fixing materials for installation on the roof including damping and yealming long straw; butting and bundling combed wheat reed; trimming, splitting and twisting spars and rods.
  • S11: Evaluate the condition of the roof prior to thatching work taking place. Assess condition of existing materials, quality of materials, covering over fixings, condition of fixings, overall thickness of thatch, factors affecting the performance of the roof.
  • S12: Prepare the roof prior to thatching. Thatch either completely stripped or stripped to a sound base coat, new structures and work surfaces prepared for subsequent thatching. Keep work areas clean and free from debris and other obstacles.
  • S13: Select the appropriate materials and use correct techniques for the specific requirements of historic or listed buildings.
  • S14: Establish suitability and quality of materials, and correctly fix the appropriate thatching materials to basic roof structures and features, to a given specification and to correct pitch, tension and density, ensuring correct cover over fixings.
  • S15: Carry out thatching works where it adjoins with other materials such as lead and brickwork.

Behaviours

  • B1: Safety-first mindset. Adhere to safe systems of work and relevant procedures including attending all safety briefings and training.
  • B2: Take responsbility for their own work and standards of work. Be aware of the limits of their own competence and seek advice when required. Cooperate with employers, other employees and site providers to ensure that their competence is maintained and up-to-date.
  • B3: Show professionalism, be prepared for work, arrive on time and present a positive attitude. Work collaboratively, show respect for others, do what has been agreed and offer assistance to others when help is needed. Be approachable, providing timely answers and explanations.
  • B4: Continue developing personally and professionally following current legislative and industry regulations and guidelines. Show a willingness to learn.

Duty 1

  • DUTY: Manage resources ready for use including thatching materials, tools, equipment and vehicles. Check prepared and fit for purpose.
  • CRITERIA FOR MEASURING PERFORMANCE: Safe loading, unloading and transporting of tools and materials, completed PPE checklist
    • K1
    • K3
    • K4
    • K5
    • K7
    • K8
    • K10
    • K13
    • S1
    • S2
    • S3
    • S4
    • S5
    • S7
    • S8
    • S9
    • S10
    • S13
    • S14
    • B1
    • B2

Duty 2

  • DUTY: Establish daily and weekly tasks and organise own work with emphasis on efficiency and safety.
  • CRITERIA FOR MEASURING PERFORMANCE: Worktime is optimised, wastage of materials minimised
    • K4
    • K5
    • K14
    • S2
    • S4
    • S5
    • B1
    • B2
    • B3
    • B4

Duty 3

  • DUTY: Establish the suitability of the work area including PPE equipment, scaffolding, ladders and an understanding of how any risk assessment affects them.
  • CRITERIA FOR MEASURING PERFORMANCE: Compliance with Working at Heights regulations, outdoor working and suitability of weather conditions
    • K4
    • K5
    • K6
    • K9
    • K13
    • S1
    • S2
    • S4
    • S5
    • S6
    • S11
    • S14
    • B1
    • B2
    • B4

Duty 4

  • DUTY: Assess the condition of the roof per agreed works, prepare the roof for thatching, understanding the differences between the different buildings to be thatched.
  • CRITERIA FOR MEASURING PERFORMANCE: Evaluate condition of roof and prepare roof for thatching
    • K2
    • K4
    • K5
    • K6
    • K9
    • K13
    • S4
    • S5
    • S6
    • S7
    • S9
    • S10
    • S11
    • B1
    • B2
    • B3

Duty 5

  • DUTY: Preparation of thatching materials including long straw, combed wheat reed and water reed; correct handling, checking and storage.
  • CRITERIA FOR MEASURING PERFORMANCE: Materials are correctly handled, checked and stored
    • K1
    • K2
    • K7
    • K8
    • K10
    • K13
    • S1
    • S2
    • S4
    • S5
    • S7
    • S8
    • S9
    • S10
    • S13
    • B1
    • B2
    • B3

Duty 6

  • DUTY: Fixing appropriate thatching materials to basic roof structure with correct depth over fixings and adequate tension.
  • CRITERIA FOR MEASURING PERFORMANCE: Correct depth over fixings and adequate tension
    • K2
    • K4
    • K5
    • K8
    • K11
    • K12
    • S1
    • S2
    • S3
    • S4
    • S5
    • S6
    • S8
    • S13
    • S14
    • B1
    • B2
    • B3

Duty 7

  • DUTY: Fix appropriate thatching materials to roof features with correct depth over fixings and adequate tensions.
  • CRITERIA FOR MEASURING PERFORMANCE: Correct depth over fixings and adequate tension
    • K2
    • K4
    • K5
    • K8
    • K11
    • K12
    • S1
    • S2
    • S3
    • S4
    • S5
    • S6
    • S13
    • S14
    • B1
    • B2
    • B3

Duty 8

  • DUTY: Use and maintain thatching tools and equipment; understand their correct use and maintenance.
  • CRITERIA FOR MEASURING PERFORMANCE: Understanding the correct use and maintenance of tools and equipment
    • K3
    • K4
    • K5
    • K8
    • K10
    • S7
    • S9
    • S10
    • B1

Duty 9

  • DUTY: Manage resources after use, clearing of site, removal of excess materials and storing tools and equipment correctly for future use.
  • CRITERIA FOR MEASURING PERFORMANCE: All tools and equipment are stored correctly for future use
    • K3
    • K7
    • K12
    • S4
    • S5
    • S7
    • S9
    • B1
    • B2
    • B3

Duty 10

  • DUTY: Quantifying thatching work and materials with the ability to work out how much material and time is required to complete a thatching job efficiently and safely.
  • CRITERIA FOR MEASURING PERFORMANCE: Ability to work out how much materials and time required to complete a thatching job efficiently
    • K4
    • K5
    • K8
    • K10
    • K13
    • K14
    • S1
    • S2
    • S3
    • S4
    • S5
    • S8
    • S11
    • S14
    • B1
    • B2
    • B4

Interested in a simple Skills Scan and Learning Progress Tracker tool for the Thatcher standard?

© Tresl Education Ltd 2024